A pro forma is a projection of a project’s costs, revenue and return, built from development cost, financing, rent, vacancy and operating expenses. It isn’t a forecast — it’s a structured set of assumptions. The useful skill isn’t building one; it’s knowing which of its assumptions are soft and testing those.
- Four blocks: development cost, revenue, operating expenses, financing
- Net operating income excludes your mortgage — mixing them flatters bad projects
- The assumptions that break pro formas: rent, interest rate, contingency, timeline
- Lenders test debt service coverage first, and they look for optimistic rent
- Every figure below is illustrative. Nothing here is a projection of returns
At around four units, a project stops responding to “can I afford the payments?” and starts requiring “does this work as a business?” A pro forma is how that second question gets answered.
This guide explains the components, shows the structure, and — more usefully — covers where they go wrong.
The components
Four blocks, in order.
1. Development cost — what it takes to create the asset.
Construction, soft costs (drawings, survey, engineering, studies), permits and municipal fees, servicing and connections, financing costs during construction, and contingency.
2. Revenue — what it earns once stabilised.
“Stabilised” means once it’s fully let and running normally, not during lease-up. Gross rent, less a vacancy allowance.
3. Operating expenses — what it costs to run.
Property tax (reassessed after the work), insurance, maintenance and repairs, utilities you pay, property management if used, and any municipal fees on registered suites.
4. Financing — how it’s funded.
Loan amount, rate, amortisation, and the resulting annual debt service.
The output:
Effective gross income − operating expenses = Net Operating Income (NOI)
And the critical structural point: NOI excludes your mortgage payment. Financing sits below the NOI line. Mixing them is the most common error non-developers make, and it flatters projects that don’t work — because a low payment can disguise a building that doesn’t perform.
A worked example
⚠️ Every figure below is a placeholder showing the structure. These are not market data, not a projection, and not a recommendation. Substitute your own.
Block 1 — Development cost
| Line | Illustrative |
|---|---|
| Construction | quoted |
| Soft costs | quoted |
| Permits and municipal fees | from your municipality’s schedule |
| Servicing and connections | the wildcard — quote it separately |
| Financing during construction | interest on drawn funds |
| Contingency | a real line |
| Total development cost |
Block 2 — Stabilised revenue
| Line | Illustrative |
|---|---|
| Gross annual rent | from your market |
| Less vacancy allowance | don’t use zero |
| Effective gross income |
Block 3 — Operating expenses
| Line | Illustrative |
|---|---|
| Property tax (reassessed) | will rise |
| Insurance | higher for a rental property |
| Maintenance and repairs | |
| Utilities you pay | |
| Management | if used |
| Total operating expenses |
Block 4 — The tests
NOI = effective gross income − operating expenses
- Debt service coverage: NOI ÷ annual debt service. Lenders look at this directly at multi-unit scale.
- Yield on cost: NOI ÷ total development cost. Compare against the market capitalisation rate and against what the capital would earn elsewhere.
If yield on cost sits meaningfully above the market cap rate, the project is creating value. If it doesn’t, you’re spending a dollar to create less than a dollar — which is a legitimate reason to stop.
The assumptions that break pro formas
Four, and being candid about them is the point of this guide.
1. Rent — the softest assumption and the most abused.
It’s the number with the largest effect on the outcome and the one most easily nudged. Use comparable local rents you can evidence, from CMHC’s Rental Market Report for your centre, adjusted honestly — downward for a below-grade unit, and downward again for vacancy.
Test it: if the project only works at the top of the achievable range, it doesn’t work. Run it at the middle and see what happens.
2. Interest rate.
A pro forma built at today’s rate says nothing about what happens at renewal. On a long hold this is a material exposure.
Test it: rerun at a rate meaningfully above your assumption. If debt service coverage collapses, you have a rate-sensitive project — which may still be fine, but you should know.
3. Contingency.
A budget with no contingency line isn’t a budget. Small projects produce surprises, and on a conversion the surprises are usually structural or underground.
Test it: ask what happens if construction comes in above budget. If there’s no answer, the contingency is doing the work of a hope.
4. Timeline.
Every month of delay is a month of carrying cost with no revenue. Delay is also where the other assumptions get worse — costs escalate, rates move, seasons are missed.
Test it: add a realistic delay to the approvals stage and see whether the project still funds itself.
The general discipline: a pro forma that only works under favourable assumptions on all four is not a plan. Vary each one and see which breaks it — that tells you what to manage.
Development cost vs operating cost
A distinction that trips people up, and it matters for how you read the numbers.
Development cost is one-time — creating the asset. It sits in the denominator of yield on cost, and it’s largely fixed once you’ve committed.
Operating cost is recurring — running the asset. It sits above the NOI line and it continues for as long as you own it.
Why the distinction matters:
Some things move between them. A better-insulated envelope raises development cost and lowers operating cost. Sound separation raises development cost and reduces turnover — an operating benefit. Spending more up front can be the cheaper choice over a hold period.
Recurring costs compound. A municipal fee on a registered suite, or a property tax increase, applies every year. A one-time cost doesn’t.
And a cost people miss entirely: the property tax reassessment. Adding legal units raises assessed value, which raises your tax — permanently. It belongs in operating expenses from year one, not as a surprise in year two.
What lenders test
At multi-unit scale, underwriting looks at the building. Three things get examined first.
Debt service coverage. Does NOI comfortably exceed annual debt service, with margin? This is the primary test.
The rent assumption. Underwriters have seen a great many optimistic pro formas and they test rent against comparables. An inflated rent assumption is the fastest way to lose credibility on an application.
The contingency and the budget’s realism. A construction budget with no contingency, or soft costs that look too low, signals a project that hasn’t been costed properly.
They also look at: your own financial position (which still carries weight at one to four units), the as-completed appraisal, evidence the units will be legal, and a realistic timeline.
What helps: bringing evidence rather than assertions. Comparable rents you can point to, a quoted budget rather than an estimate, and a schedule that accounts for permit review.
Our financing page covers what’s available at each scale.
How to sanity-check one
Six questions to ask of any pro forma — including your own, and especially one someone else prepared.
1. Does NOI exclude the mortgage? If financing is above the NOI line, the whole thing is misconstructed.
2. What vacancy rate is assumed? Zero is not an answer. Check the current figure for your centre.
3. Where did the rent come from? “Market” isn’t a source. Comparable units, evidenced.
4. Is there a contingency, and how big? No line means no contingency.
5. What happens at a higher interest rate? If it hasn’t been tested, it hasn’t been thought about.
6. Is the property tax reassessed? Using current tax on an improved property understates operating expenses every year.
And one more: does the pro forma have a version where the project doesn’t work? A model that produces an attractive result under every assumption isn’t a model — it’s a sales document.
Our development management page covers who holds these numbers on a project, and multiplex development covers the scale where they matter.
Get the inputs right before modelling the outcome
A pro forma is only as good as its four soft assumptions — and two of them, cost and feasibility, depend entirely on what your property can actually support.
HouseLyft’s free property assessment establishes that. If your project is at a scale where the numbers need modelling properly, get qualified.
This guide explains financial modelling in general terms and is not financial or investment advice. Every figure in the worked example is illustrative and no return is projected, promised or implied — confirm all inputs with current market data and professional advisers.